Removing bottlenecks to advance wind and hydropower projects
On the afternoon of August 19, Thai Nguyen Provincial People's Committee held a conference on the development of wind-power and hydropower projects in the province. Comrade Duong Van Luong, Vice Chairman of Thai Nguyen Provincial People's Committee, chaired the conference. Attending the conference were leaders of departments, sectors, and localities, Thai Nguyen Power Company, as well as project owners and investors.
Anh-tin-bai

Scene of the Conference

Under the power-source development plan through 2030, the province has 7 wind-power projects with total capacity of 766 MW; 14 hydropower projects with total capacity of 74.1 MW; 5 centralized solar-power projects with capacity of 200 MW; 2 waste-to-energy projects with capacity of 20 MW; and 5 biomass-power projects with capacity of 95 MW.

Anh-tin-bai

Leaders of the Department of Industry and Trade reporting on project implementation

For hydropower, 7 plants are currently generating electricity. Several projects are being expedited, including Nam Cat 2 Hydropower Plant, which is more than 96% complete, and Khuoi Noc 2 Hydropower Plant, which has reached approximately 95% and is expected to be completed in August 2026. Other projects are completing procedures and site clearance, with the aim of commencing construction in 2026.

Seven wind-power projects with a combined capacity of 766 MW are currently being surveyed and assessed for wind potential, while dossiers for investment-policy approval and feasibility studies are being prepared. Of these, the investor for Thien Long Cho Moi Wind Power Plant has been approved; construction is expected to begin in June 2027, with commercial operation scheduled for December 2028. The remaining projects are continuing to complete their records, assess wind potential, and carry out investment procedures.

Anh-tin-bai

Representative of Thien Long-Bac Kan Wind Power Joint Stock Company discussing at the Conference

At the conference, delegates focused on reviewing progress and clarifying difficulties in planning, investment, site clearance, grid connection, and legal procedures, while clearly defining responsibilities and solutions to remove obstacles and accelerate project progress.

Anh-tin-bai

Vice Chairman of Thai Nguyen Provincial People's Committee Duong Van Luong delivers directive remarks

In his directive remarks, Comrade Duong Van Luong, Vice Chairman of Thai Nguyen Provincial People's Committee, directed investors to strengthen their financial capacity and project management and proactively add personnel and resources to ensure progress as committed. Localities, departments, and sectors should strengthen coordination, closely follow each project, and promptly remove difficulties, especially in site clearance. Thai Nguyen Provincial People's Committee will establish specific timelines and conduct periodic accountability reviews for each project. Where delays result from subjective causes, the investor or relevant agency or locality must be held accountable. For delayed projects with protracted implementation, the province will consider extensions or adjustments in accordance with the law. To accelerate site clearance, he requested that investors sign contracts with the Provincial Land Fund Development Center and coordinate with local authorities for implementation. Localities should proactively coordinate with investors to resolve difficulties related to planning and forest-land conversion.

Thu Trang
thainguyen.gov.vn
image advertisement

image advertisement image advertisement
Access Statistics
  • Đang online: 1
  • Hôm nay: 1
  • Trong tuần: 1
  • Tất cả: 1

Managing agency: People's Committee of THAI NGUYEN PROVINCE

Copyright (C) 2009-2010 belongs to Thai Nguyen Province People's Committee

Head office: No. 88, Hung Vuong street, Thai Nguyen Email: portal@thainguyen.gov.vn Phone: 0208.3851149 Fax: 0208.3851149

Specify the source "en.thainguyen.gov.vn" when releasing information from this website