ĐT.265 connecting road to Bac Ninh Province to be completed before September 30, 2026
On the morning of June 17, Comrade Vuong Quoc Tuan, Member of Party Central Executive Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee, conducted an on-site inspection and urged progress on the implementation of the ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District (now Dan Tien Commune) to Bac Giang Province (now Bac Ninh Province), and the Dong Xe - Son Cam Resettlement Area Project in Quan Trieu Ward.
Anh-tin-bai

Chairman of the Provincial People's Committee and the working delegation inspecting the ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District to Bac Giang Province

Anh-tin-bai

Progress of the ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District to Bac Giang Province currently reaches 43.41% of total volume

The ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District (now Dan Tien Commune) to Bac Giang Province (now Bac Ninh Province) spans a total length of more than 6 km and is designed to Class III mountain road standards. The road begins at an intersection with ĐT.265 at Km21+500 and ends at a connection with the road linking National Highway 37 and National Highway 17 in Bac Ninh Province. The project's total investment exceeds VND 291 billion from state budget funds. According to reports, after more than one year of implementation, the completed volume has only reached 43.41%; the biggest challenge at present is land clearance, as 2 households have yet to agree on a compensation plan.

Anh-tin-bai

Chairman of the Provincial People's Committee directing that no timeline adjustment be made to the ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District to Bac Giang Province, with completion required by September 30, 2026 as committed by the investor

Following the on-site inspection, the Chairman of the Provincial People's Committee sternly criticized the implementation progress of the ĐT.265 Connecting Road Project from Binh Long Commune, Vo Nhai District to Bac Giang Province for the past time. He noted that despite the prolonged implementation period, the completed construction volume has not met the set requirements; capital disbursement to contractors has also not kept pace with the construction schedule. Emphasizing that this is an infrastructure project of significant importance for inter-regional connectivity, helping drive socio-economic development, the Chairman of the Provincial People's Committee directed that the project implementation timeline not be adjusted. The full-route completion milestone is set for September 30, 2026, as committed by the investor.

To ensure the schedule, the Chairman of the Provincial People's Committee required Dan Tien Commune to coordinate with the Provincial Land Fund Development Center to complete the handover of all remaining cleared land to the construction unit before July 5, 2026. The local political system, particularly the heads of Party committees and government authorities, must directly engage, intensify public communication and mobilization, and explore and maximize the use of applicable support policies as prescribed to build consensus in land clearance efforts.

Regarding contractors, he required them to take advantage of favorable weather before the rainy season, maximize the deployment of labor and equipment, and conduct continuous construction to recover lost progress on a daily basis. The investor must closely monitor the construction site, promptly address emerging challenges, and strictly adhere to capital disbursement requirements as directed by the Provincial People's Committee.

Anh-tin-bai

Chairman of the Provincial People's Committee and the working delegation inspecting the Dong Xe - Son Cam Resettlement Area Project in Quan Trieu Ward

Regarding the Dong Xe - Son Cam Resettlement Area Project in Quan Trieu Ward, this is a resettlement area serving the Huu Cau Dike Construction Project from Cao Ngan Bridge to Thac Huong Dam, which is part of the Flood Control Works System of the Central Zone of Thai Nguyen Province. The project is currently completing the investment procedures and is expected to be approved on June 20, 2026 to proceed with the subsequent steps.

Anh-tin-bai

Leadership of Quan Trieu Ward reporting to Chairman of the Provincial People's Committee on the resettlement area project serving the Huu Cau Dike Construction Project

At the inspection, the Chairman of the Provincial People's Committee emphasized that this project serves a provincial project of urgent priority and is thus also classified as an urgent project, which must be implemented with urgency and determination. He required Quan Trieu Ward to focus on land clearance, ensuring construction proceeds on a rolling basis as each section of land is cleared; accelerate the pace of technical infrastructure construction and strive to ensure the resettlement land can be handed over to households by November 30, 2026, creating favorable conditions for the flood control project to be implemented as planned.

Huong Lan – Thanh Chung
thainguyen.gov,vn
image advertisement

image advertisement image advertisement
Access Statistics
  • Đang online: 1
  • Hôm nay: 1
  • Trong tuần: 1
  • Tất cả: 1

Managing agency: People's Committee of THAI NGUYEN PROVINCE

Copyright (C) 2009-2010 belongs to Thai Nguyen Province People's Committee

Head office: No. 88, Hung Vuong street, Thai Nguyen Email: portal@thainguyen.gov.vn Phone: 0208.3851149 Fax: 0208.3851149

Specify the source "en.thainguyen.gov.vn" when releasing information from this website